Las Vegas Motor Speedway's Public Relations Department will be providing weekly construction updates as the speedway undergoes its multi-million dollar facelift, which will result in a new fan interactive garage area, a pit road closer to the grandstands, resurfaced and re-banked racing surface and state-of-the-art media center.


In the past week, construction crews have completed the following tasks:

  • Begun the construction of the new pit wall in the speedway's tri-oval.
  • Completed the demolition of Garage 1 to make way for the new Busch Series garage.
  • Begun the demolition of the retaining wall in turns 1 and 2.
  • Started the process of replacing the vehicular tunnel to allow for fill to increase the banking in the turns.
  • Completed the removal of the old racing surface.